Cabinet approves construction of doubling of line with electrification between
New Delhi: The Cabinet Committee on Economic Affairs, chaired by the Prime Minister Shri Narendra Modi, has approved the construction of double line with electrification between Vanchi-Maniyachchi- Nagercoil via Tirunelveli in Tamil Nadu.
The total length of the line will be 102 km. The estimated cost of the Project will be Rs.1003.94 crore and completion cost of Rs.1114.62 crore with 5% escalation per annum.
The project is likely to be completed in four years by 2020-21. The project will generate direct employment during construction for 24.48 lakh mandays.
The project would not only speed up the operation of goods and coaching trains, but also provide additional capacity for meeting the increase in traffic in future.
Background:
Vanchi-Maniyachchi- Nagercoil via Tirunelveli is an important trunk route serving the Southern end of Tamil Nadu and Kerala. The section is heavily passenger oriented which also serve the goods traffic from nearby ports. Present line capacity of the section has already gone beyond 90% which is causing detention to the moving trains. Line capacity of this route needs to be enhanced to meet the demands for additional trains and smooth movement of trains through the route. Hence, doubling of Vanchi-Maniyachchi- Nagercoil via Tirunelveli with electrification needs to be taken up.
News Must Read
- CIL’s capex up 6.5% to highest Rs.19,840 Crores in FY 2024
- SCOPE presents SCOPE PREMIER LEAGUE
- MCL Ib Valley Washery commenced commercial operation
- HAL bags Rs 65,000 Cr tender by Defence Ministry
- PSBs' growth output superseded Private Lending firms
- Northern Coalfields Limited CMD inspects Amlohri Area
- SCOPE organizes Public Sector Day celebrations
- IOCL Final Dividend Announcement Expected at April 30 Board Meeting
- Steel Cutting Ceremony of Indian Navy held at HSL Vishakapatnam
- DIPAM declines PFC-REC debt resolution proposal for KSK Mahanadi project