NTPC Kaniha Power Plant to suffer as MCL Continues to reel under Disturbances
Sambalpur: Stoppage of coal mining and dispatch due to external disturbances in Kaniha project of Mahanadi Coalfields Limited (MCL) continued on tenth day today, leading to the worsening crisis in NTPC Kaniha in Talcher coalfields.
The eight-million-tonne project Kaniha OCP, which is linked to fuel NTPC Kaniha, was stopped by the villagers of Pathermunda demanding employment.
After the parleys at project-level failed to yield any positive result at the unit level, the top management had also sought intervention at higher levels. But the mine continues to remain at the halt.
Kaniha project, which produced over 7000-tonne coal a day, has seen the highest 53 days of stoppage of work in MCL during the current financial year 2018-19.
During the current fiscal, MCL has continued to suffer in Talcher coalfields due to unrealistic demands sprouting from various socio-political quarters in Talcher coalfields. The company’s production has gone down by over 25 million tonnes, leading it struggling to register positive growth during FY’19.
Against 143 million tonne coal produced during 2017-18, MCL is running with seven per cent negative growth due to continuous stoppages in Talcher coalfields, which contributes to over 65 per cent of total coal produced by the company.
Similarly, the six-million-tonne capacity Balram OCP of Hingula Area is paralysed since 17th of February 2019. The 10-million tonne capacity Hingula Area in Talcher coalfields has been the second highest in terms of stoppages as it has remained closed for over 47 days during the current fiscal.
The month of January 2019 has remained the most-affected period for MCL as projects in Talcher coalfields, which were to produce over nine million tonne coal, remained stopped for around about five days.
The mines of MCL work 24x7 to meet the energy demand of the nation, but the stoppage of work due to external disturbances on illegal grounds may lead to the shortage of coal to power plants in southern states as well.
Read Also : Indigenous Technology Cruise Missile successfully flight-tested by DRDO
News Must Read
- CIL’s capex up 6.5% to highest Rs.19,840 Crores in FY 2024
- SCOPE presents SCOPE PREMIER LEAGUE
- MCL Ib Valley Washery commenced commercial operation
- HAL bags Rs 65,000 Cr tender by Defence Ministry
- PSBs' growth output superseded Private Lending firms
- Northern Coalfields Limited CMD inspects Amlohri Area
- SCOPE organizes Public Sector Day celebrations
- IOCL Final Dividend Announcement Expected at April 30 Board Meeting
- Steel Cutting Ceremony of Indian Navy held at HSL Vishakapatnam
- DIPAM declines PFC-REC debt resolution proposal for KSK Mahanadi project