BHEL commissions two units of 6X170 MW Punatsangchhu-II Hydroelectric Project in Bhutan

This project is part of a bilateral agreement between the Government of India and the Royal Government of Bhutan. PHEP-II is a greenfield hydroelectric project situated in the Wangdue district of Western Bhutan.

BHEL commissions two units of 6X170 MW Punatsangchhu-II Hydroelectric Project in Bhutan
BHEL commissions two units of 6X170 MW Punatsangchhu-II Hydroelectric Project in Bhutan

State-run Bharat Heavy Electricals Limited has reached another significant milestone in Bhutan by successfully commissioning two units of the 6x170 MW Punatsangchhu-II Hydroelectric Project (PHEP-II).

This project is part of a bilateral agreement between the Government of India and the Royal Government of Bhutan. PHEP-II is a greenfield hydroelectric project situated in the Wangdue district of Western Bhutan.

Significantly, the Francis Turbine installed in the project is designed to operate at a rated head of 241 meters – the highest for any Francis Type Hydro Turbine in Bhutan. On commissioning all six units, the expected annual power generation will be 4,357 gigawatt-hours. Unit 1 and 2 of the 6x170 MW PHEP-II were synchronized on December 16 and 17, 2024, respectively, as per the release.

Join PSU Connect on WhatsApp now for quick updates! Click here

Read Also : Third Wave Coffee appoints Akshat Arora as Marketing Director

BHEL’s scope in PHEP-II comprises design, manufacture, supply, installation, and commissioning of Electro-Mechanical works for 6x170 MW Vertical Francis Turbines & matching Synchronous Generators, Control & Monitoring (SCADA) Systems, Generator Transformers, Shunt reactor, Busduct, Pothead yard along with associated auxiliaries.

The equipment has been supplied by BHEL’s units at Bhopal, Jhansi, Rudrapur, Bengaluru, and its Transmission Business Group, while erection and commissioning on site was carried out by the company’s Power Sector-Eastern Region division, Kolkata. BHEL has executed major projects like 4x84 MW Chukha, 4x15 MW Kurichhu, 6x170 MW Tala, and 4x180 MW Mangdechhu in Bhutan to date.

Read Also : NLCIL introduces free special bus service for intellectually challenged school children

With the commissioning of these two units at PHEP-II, BHEL’s contribution to the total installed capacity in Bhutan now stands at nearly 89%. Further strengthening its footprint in the region, BHEL is currently executing an order for 6x200 MW Punatsangchhu-I HEP, in addition to PHEP-II in Bhutan.

Apart from the above, BHEL is executing the 4x225 MW Arun-3 HEP and 2x20 MW Rahughat HEP in Nepal. Notably, BHEL has successfully executed over 3.8 GW of Hydro Projects abroad with more than 2.8 GW of Hydro Projects under execution.