Repair of iconic Saraighat bridge carried out in record time railway-news

 

 

GUWAHATI:  As many as 336 numbers of structural steel members called stringers of the iconic Saraighat Bridge over the River Brahmaputra here have been replaced in a duration of just eight and half months. Stringers are steel beams positioned along the length of the bridge on which the rails of the track are directly placed, according to P J Sarma, the chief public relations officer of Northeast Frontier Railway.
 
Load from a passing train are first transferred to the stringers and from them further to other members. Replacement of inner stringers is a very difficult task as it requires removal of outer stringers. Workers have to position themselves in very limited working space and the work is to be done by stopping the movements of trains i.e. a “traffic block”.
 
Saraighat bridge is the first rail-cum-road bridge over the mighty River Brahmaputra near Guwahati. The 1.4 kms long double – decker bridge which connects both North and South banks of Brahmaputra River was opened for traffic in 1963. Originally the bridge was constructed to run two MG or one BG train.
 
Later, during gauge conversion in 1982-83 the rail stringers were replaced making provision of MG / BG combined track i.e. on which both MG and BG traffic could ply. Now it has one BG track over it. The bridge has already completed 54 years of service. During the more than 54 years of service, the flanges of Rail Stringers get corroded. Hence they needed replacement or strengthening work.
 
Since March 2017 to June 17, 2017 only 14 numbers new and 19 numbers strengthened rail stringers could be replaced due to non-availability of traffic block. However, later regular scheduled traffic block for one hour 45 minutes on every Tuesday, Thursday and Saturday was allotted. This resulted into an increase of replacement of stringers from two to six numbers per block. Accordingly, the total work involving 336 stringers was completed on November 15,2017 in eight and half months as against the target date of December 31, 2017.
 
It can be mentioned here that similar work was done in the year 2007 for replacement of outer stringers, which took about 3 years to complete. But this time inner stringers were changed (which requires almost double the quantum of work under traffic block) within a much shorter time, thus minimizing the disruption to traffic due to proper planning.


Posted Date :  02-01-18

Categories : railway-news

Tag Cloud: railway-news

Similar news

Indian Railways finalised tender for Vande Bharat Type Train sets

New Delhi: Indian Railways has finalised the tender for Design, Development, Manufacture, Supply, Integration, Testing and Commissioning of IGBT based 3-Phase Propulsion, Control and Other Equipment for Train Sets (Vande Bharat Type Train sets) for 44 Rakes of 16 Car each on Jan 21, 2021. The pro
Posted Date :  22-01-21

Read more

Railways to restart E-catering services for passengers

New Delhi: The Indian Railways under the leadership of Hon’ble Minister of Railways and Minister for Commerce and Industry and Consumer Affairs, Food and Distribution Sh. Piyush Goyal has achieved a number of milestones recently in partial fulfillment of the vision of Hon’ble Prime Minis
Posted Date :  22-01-21

Read more

Indian Railways will run Special Trains for Magh Mela

New Delhi: Indian Railways has announced to run Magh Special Trains keeping the view of Magh Mela in Sangamnagar Prayagraj. On the one hand, during the Magh Mela which is going to be held in the midst of the Corona epidemic, while the Mela administration is making special arrangements for the pilgri
Posted Date :  13-01-21

Read more

NHSRCL launched the LiDAR survey for 800-km Delhi-Varanasi route

New Delhi: On Sunday, the National High-Speed Rail Corporation Limited (NHSRCL) launched the LiDAR survey for the Delhi-Varanasi route from Uttar Pradesh's Greater Noida, wherein a helicopter fitted with state-of-the-art aerial LiDAR and imagery sensors will capture data related to the ground su
Posted Date :  12-01-21

Read more

Shri Piyush Goyal reviewed the ongoing USBRL National Project

Jammu and Kashmir: Shri Piyush Goyal, Minister for Railways, Commerce & Industry and Consumer Affairs, Food & Public Distribution.  reviewed the progress of the ongoing USBRL National Project in Jammu & Kashmir. Shri. V.K. Yadav, CEO & Chairman Railway Board, and Shri. Ashutosh
Posted Date :  30-12-20

Read more

Inaugural run of special new train Tinsukia - Tambaram

Assam: Special Train NEW TINSUKIA- TAMBARAM  EXPRESS commenced its inaugural run via Bogibeel Bridge-North Lakhimpur-Rangiya route. Cities and towns located in the North bank of Brahmaputra are getting connected to important cities in the country through rail.  New Tinsukia is a rail
Posted Date :  30-12-20

Read more

IRCTC website will give more ease of booking online

New Delhi: Shri Piyush Goyal, Minister for Railways and Commerce & Industry and Consumer Affairs, Food & Public Distribution, reviewed the upgradation being worked for the Eticketing system. The Minister sought that Eticketing web site should provide holistic convenience to the passengers
Posted Date :  25-12-20

Read more

Indian Railway initiates to grow more Parcel business

New Delhi: Hon’ble Minister for Railways Shri Piyush Goyal conducted a review of Railways’ Parcel business which was attended by the Members of Board and other officials of Railway Board and CRIS.   During the last few months, Indian Railways has brought in several initia
Posted Date :  22-12-20

Read more

Shri Piyush Goyal review the meet on various projects of railways

New Delhi: Minister Piyush Goyal reviewed the progress of various projects related to the modernization of Indian Railways, including rail electrification, modern signaling system & centralized traffic control.   He also discussed ways to complete them in an efficient and timebou
Posted Date :  14-12-20

Read more

Indian Railways canceled many trains till 31 January due to fog

New Delhi: First the Covid-19 hits to stop the services of Indian railways and now the winter season has started and the railway stops operating some trains due to fog. Due to this, a decision has been taken to cancel many trains in many parts of the country. Apart from this, the railway has also
Posted Date :  14-12-20

Read more

Rail Ministry withdrawn its order- No general tickets yet

New Delhi: After 48 hours the Ministry of Railways has withdrawn its decision on issuing general tickets for the passengers. Yet the passengers will not be able to travel on general tickets right now.    Passengers with confirmed tickets can be avail the services and travel. The
Posted Date :  11-12-20

Read more

The 6 km long Habibganj-Bhopal 3rd line project completed

Bhopal: The third line railways project between Habibganj-Bhopal station is been completed and ready to run. The CRS trolley inspection and speed trial of 5.93 km long Habibganj-Bhopal 3rd line was successfully conducted on November 25, 2020. with a speed of 120 kmph. This is an unimaginable and
Posted Date :  27-11-20

Read more