EIL achieves a key milestone on a succession of RCC tank foundation

EIL achieves a key milestone on a succession of RCC tank foundation
Aerial view of the tank pad during concreting

New Delhi: Team EIL at Dangote Refinery and Petrochemical Project (DRPP), Nigeria achieves a key milestone with the successful completion of the RCC tank foundation with 6789 Cum of single pour concrete for the tank pad in TF-61. 
 
This is the second of the three such tank pads with a diameter of 93 Meters and a depth of 1 Meter. The concrete pouring was completed within 56 hours.
 
EIL has built an unmatched track record of providing services to major Hydrocarbon, Chemicals & Fertilizers, Mining & Metallurgy, Infrastructure, and Power projects.