Badarpur plant must function in summer to meet high demand
NEW DELHI . Delhi power secretary Varsha Joshi said, "We will have to reopen the Badarpur plant as soon as summer starts. We will need Badarpur power plant until we have the Tughlaqabad sub-station ready. The work has already been awarded and it has to be completed by March 2018."
EPCA members said the substation was supposed to be completed by 2015-16. "Give us a time-frame for the 400KV Tughlaqabad station first. We will allow you to reopen Badarpur in summer on the condition that you devise a time-frame for Tughlaqabad," an EPCA member said. TImes of India
Read Also : KABIL inks MoU with CSIR-NGRI for advancing geophysical investigations in critical and strategic minerals sector
News Must Read
- SJVN Limited inaugurates India's first Multi-purpose Green Hydrogen Pilot Project
- KRDCL, RVNL JV emerges as the Lowest Bidder for Redevelopment of Thiruvananthapuram Central Railway Station
- REC Ltd. has incorporated subsidiary company BPTL
- Hon’ble Vice President of India Confers `Outstanding PSU of the Year’ Award on HAL
- BharatPe Launches India’s first All-in-One Payment Device
- NBCC registers historical Performance in FY2023-24
- RuPay Unveils Link it, Forget it Campaign at IPL 2024 to Promote RuPay Credit Card on UPI
- NTPC Green Energy Limited Inks MoU with Indus Towers Limited
- CIL’s capex up 6.5% to highest Rs.19,840 Crores in FY 2024
- SCOPE presents SCOPE PREMIER LEAGUE