Supreme Court: Contract Clause Bars Pre-Reference Interest in NEEPCO Case
New Delhi: The Supreme Court on 22 September 2026 held that a standard contractual clause in public works contracts can completely bar the award of pre-reference interest by an Arbitral Tribunal.
A bench of Justices Pamidighantam Sri Narasimha and Alok Aradhe allowed the appeal filed by North Eastern Electric Power Corporation Limited (NEEPCO) against Astra Construction Private Limited.
Background
The Arbitral Tribunal had awarded a principal sum of ₹3.30 crore along with pre-reference interest at 12% per annum. The Commercial Court set aside the pre-reference and pendente lite interest, relying on the decision in Sayeed Ahmed. The Meghalaya High Court restored the interest by treating Clause 54 of the GCC as identical to the narrower clause examined in Harish Chandra.
Supreme Court’s Ruling
The Court held that Clause 54 of NEEPCO’s General Conditions of Contract is not the same as the clause in Harish Chandra.
Clause 54 expressly bars claims for interest or damages in two distinct situations:
-
Money or balance lying with the Corporation due to any dispute, and
-
Any delay in making periodical or final payments,
followed by the wide words “or in any other respect whatsoever”.
This wording matches the clauses upheld as complete bars in Sayeed Ahmed and Jaiprakash Associates v. THDC. Under Section 31(7)(a) of the Arbitration and Conciliation Act, 1996, once the contract prohibits interest, the Tribunal has no power to award pre-reference interest.
Final Order
-
Appeal allowed
-
High Court judgment restoring pre-reference interest set aside
-
No order as to costs
The Court clarified that party autonomy under the 1996 Act prevails, and an express contractual bar is sufficient to exclude the arbitrator’s power to grant pre-reference interest.