As a part of the Reactor-Regenerator (RR) package, the erection of the bottom section of the Regenerator for Petrochemical Fluidized Catalytic Cracker (PFCC) Unit at HRRL - Barmer Project was successfully completed on 3rd January 2023.
![HRRL's Barmer Project completed successfully](https://www.psuconnect.in/sdsdsd/HRRL_Barmer_Project_completed_successfully.jpg)
HRRL's Barmer Project completed successfully
NEW DELHI- As a part of the Reactor-Regenerator (RR) package, the erection of the bottom section of the Regenerator for Petrochemical Fluidized Catalytic Cracker (PFCC) Unit at HRRL - Barmer Project was successfully completed on 3rd January 2023.
The RR package is the Heart of the PFCC unit and is one of the most critical packages. Erection of Regenerator section bottom part 111-R-1102 was successfully accomplished using a 2000 MT ringer crane and 650 MT tailing crane at EL 118.20 M.
Read Also : IndusInd Bank Q1 FY25 results, net profit at 2% YoYNews Must Read
- Karnataka Bank Announced record Q1 Net Profit at Rs. 400.33 CR
- NTPC, BHEL shares soar higher amid JV announcement in Budget 2024
- BEL signs tripartite MoU for manufacture of indigenised ammunition
- Goa Shipyard Limited launched first indigenous P1135.6 Frigate
- Chandan Sinha appointed as Non-Executive Part Time Chairman of RBL Bank
- OIL and Dolphin Drilling signs contract for hiring of Blackford Dolphin
- Cmde D.K. Murali, IN (Retd.) Joins as CMD of BECIL
- Samir Chandra Saxena Appointed as Director (Market Operation) of GRID-INDIA
- MOIL CMD bags Title 'CEO of the Year'
- ONGC sign MoU with GSI to advance geothermal exploration in Ladakh