Numaligarh Refinery Limited achieved milestone

The final installation was completed on 28th November 2024, using a 1600 MT Demag crane supported by a 600 MT trailing crane.

Numaligarh Refinery Limited achieved milestone
Numaligarh Refinery Limited achieved milestone

 

New Delhi: Numaligarh Refinery Limited (NRL) achieved a significant milestone in its expansion project with the successful installation of the 60-meter-tall CDU Column. This massive 400 MT structure, one of the largest ODCs handled at the site, was efficiently assembled on-ground before being erected. The innovative approach of assembling the skirting, platforms, piping, and insulation around the column at ground level has set new benchmarks for efficiency and safety.

Join PSU Connect on WhatsApp now for quick updates! Click here

Read Also : RailTel bags work order from CWC worth Rs 96.99 crore

By executing major jobs such as 65 MT of platform and support installations, and approximately 4800 Inch Meter (IM) of piping work on the ground, the project team was able to significantly minimize activities at height, reducing risks and ensuring safer operations. This method also expedited sequential tasks, avoiding time-consuming scaffolding work post-erection.

Read Also : Cuddalore Will Soon Have One of the Biggest Libraries in Tamil Nadu Says Collector at Neyveli Book Fair

The final installation was completed on 28th November 2024, using a 1600 MT Demag crane supported by a 600 MT trailing crane. NRL extends its heartfelt thanks to its valued stakeholders, including Managing PMC, M/s Technip, and the EPC agency, M/s Thyssenkrupp, for their contribution to this milestone achievement.

Read Also : Bank of Baroda issues advisor amid All India Strike on 9th July

Disclaimer: All the articles and given information on this page are information based and provided by other sources . For more read Terms & Conditions