NHPC's Dibang Multipurpose Project Achieves Key Excavation Milestone
NHPC’s 2880 MW Dibang Multipurpose Project completed 550m of diversion tunnel excavation in November 2025, overcoming challenging geology. The project will feature one of the world's tallest concrete gravity dams.

Loading ad...
New Delhi: NHPC’s 2,880 MW Dibang Multipurpose Project has achieved a major construction milestone with 550 meters of heading excavation completed in its Diversion Tunnels as of November 2025.
The project is currently advancing five tunnels, each with a 12-meter diameter, totaling 6.3 km in length.
Despite challenging and varied geological conditions, this progress represents a significant step forward. Once completed, the Dibang Dam will rank among the tallest concrete gravity dams globally, reinforcing NHPC’s leadership in large-scale hydroelectric and multipurpose infrastructure development.