Second TBM Assembly Begins at Sawli for Mumbai–Ahmedabad Bullet Train Tunnel
Mumbai: The assembly of the second Tunnel Boring Machine (TBM) has commenced at Sawli, near Ghansoli in Mumbai, marking another significant milestone for the Mumbai–Ahmedabad High-Speed Rail corridor. The machine will begin tunnelling from Sawli towards Vikhroli.
Complex Underground Assembly at 39 Metres Depth
The TBM is being assembled 39 metres below ground level in a highly constrained shaft environment. Due to limited space at the Sawli launch shaft, the assembly process has been meticulously planned and executed to ensure precision and safety.
A key milestone achieved today was the lowering of the gantry weighing 190 metric tons, measuring:
- Length: 18 metres
- Width: 10 metres
- Height: 9 metres
Critical Role of TBM Gantries
Each TBM is equipped with four gantries, which will be attached to the main shield assembly and cutterhead. These gantries will travel along the entire excavated tunnel length and support critical operations such as:
- Continuous excavation
- Waterproofing systems
- Tunnel lining segment installation
- Logistics and equipment support
Tunnelling Drive to Begin in July 2026
The TBM’s initial tunnelling drive is expected to commence in July 2026, advancing underground connectivity for India’s first high-speed rail corridor. This development represents a major step forward in the construction of the underground section of the bullet train project in Mumbai.