Delhi Metro advances Janakpuri Noida launch deadline to September 2017
NEW DELHI . Revising its December 2017 deadline, the Janakpuri-Noida ‘Magenta Line’ of the Delhi Metro Rail Corporation (DMRC) will be ready to be commissioned by September, while a segment of the ‘Pink Line’ is also likely to be launched then.
The revised figures form part of the progress report of DMRC’s Phase III project. Line 8, christened the Magenta Line, will connect west Delhi to Noida via IGI Airport’s domestic terminal. Stretches of it are likely to be commissioned by April and June, respectively.
Battling land acquisition issues, the project had missed its December 2016 deadline. “Progress of civil works upto December 2016 is 95.97%. The Botanical Garden-Kalkaji section is likely to be opened by April 2017. The entire 34-km-long line is targeted for completion in September 2017,” the report said.
Although the Delhi Metro has not set any deadline for the full commissioning of the 59-km-long Pink Line, which is set to be the longest connecting line, a segment of it between the Majlis Park-Lajpat Nagar section, is targeted to be completed by September 2017. Moneycontrol
Read Also : WAPCOS CMD conferred with PSU Samarpan Award
News Must Read
- Sushil Sharma assumes additional charge of CMD, and Director (Personnel) of SJVN Limited
- Coal India Limited Board recommends final dividend, here to know
- Dr. Subhransu Sekhar Acharya assumes charge of NSIC CMD
- CIL reports mixed bag of results for Q4 of FY23-24
- NMDC's Promising Start to FY25, Targets 50 Million Tonnes
- RITES to take assessment for Vande Bharat Trains
- RBI cancels Certificate of Registration of Acemoney (India) Limited due to irregular lending practices
- Coal India Production rises by 7 percent in April
- WAPCOS became second Indian PSU in ADB Consulting
- Power Grid appoints Satyaprakash Dash as CS and Compliance Officer