PGCIL completes Wardha-Dichpally transmission line
HYDERABAD: The Telangana Transco on Monday announced the successful installation and test charge of two new 400 kv feeder bays at the 400 kv Dichpally sub-station. The Power Grid Corporation of India Ltd (PGCIL) has already announced the completion of the Wardha-Dichpally transmission line to evacuate power from Chhattisgarh.
The two power discoms are expected to get 1,000 mw power from Chhattisgarh from March second week. The power purchase agreement in this regard was signed in September 2015.
Work on the 400 kv Maheshwaram sub-station and the connected lines, which hold the key to availing power supply from Chhattisgarh state, is progressing swiftly and the executing agencies have assured of their completion by April.
Read Also : WAPCOS CMD conferred with PSU Samarpan Award
News Must Read
- Sushil Sharma assumes additional charge of CMD, and Director (Personnel) of SJVN Limited
- Coal India Limited Board recommends final dividend, here to know
- Dr. Subhransu Sekhar Acharya assumes charge of NSIC CMD
- CIL reports mixed bag of results for Q4 of FY23-24
- NMDC's Promising Start to FY25, Targets 50 Million Tonnes
- RITES to take assessment for Vande Bharat Trains
- RBI cancels Certificate of Registration of Acemoney (India) Limited due to irregular lending practices
- Coal India Production rises by 7 percent in April
- WAPCOS became second Indian PSU in ADB Consulting
- Power Grid appoints Satyaprakash Dash as CS and Compliance Officer