PowerGrid helps to restore power to DIU after Taukte cyclone
POWERGRID was assigned to restore 220 kV Timbdi-Dhokadva and Savarkundla-Dhokadva Transmission Lines feeding power to Diu following extensive damage Taukte cyclone.
Representational Image
New Delhi: Power Grid Corporation of India Limited (POWERGRID), a Maharatna CPSU under the Ministry of Power, Government of India, was assigned the task of restoring 220 kV Timbdi-Dhokadva and Savarkundla-Dhokadva Transmission Lines feeding power to Diu following extensive damage due to the Taukte cyclone.
POWERGRID took up the restoration on a war footing and a team of about 600 personnel including expert manpower from POWERGRID worked round-the-clock for early restoration of the lines in which about 33 towers collapsed besides suffering other damage. POWERGRID used the Emergency Restoration System to set up eleven towers and also constructed 10 new towers restoring the 220 kV Timbdi-Dhokadva line on 28th May 2021.
With the commissioning of this line, fifteen 66 kV Substations of GETCO could be energized to provide a reliable power supply to Diu and nearby areas. Work for restoration of the Savarkundla-Dhokadva line is currently under progress.
The Ministry of Power in a tweet said, “It’s a matter of great pleasure that with the kind support of MoP, POWERGRID and all concerned, 220 kV Dhokadva substation has been charged through 220 kV Timbdi - Dhokadva line and load taken today on 28th May at 20:24 hrs.”
POWERGRID is at the forefront of helping state utilities across the country restore power transmission lines affected by natural calamities.
Read Also : Indian Air Force ushers in Digital Transformation with DigiLocker IntegrationNews Must Read
- NCL General Manager (Finance) D Sunil Kumar recommended for SECL Director (Finance)
- Bank of Maharashtra Q4 results, Net Profit increased by 44.95 percent to Rs 1,218 crore
- Axis Bank Overtakes Kotak Mahindra Bank to Become India's Fourth Most Valued Lender
- LIC cuts stakes in major PSU stocks
- SJVN CMD Geeta Kapur Inaugurates Construction Works at Sunni Dam Project in Himachal Pradesh
- PESB Selects R Veerabahu as Director (Finance) for Braithwaite & Co. Limited
- Grew Energy bags largest order of 200 MW Contract of SECI's Auction
- CPCL Reports 39% YoY Drop in Q4 Net Profit, Declares Rs 55 per Share Dividend
- SJVN Limited inaugurates India's first Multi-purpose Green Hydrogen Pilot Project
- KRDCL, RVNL JV emerges as the Lowest Bidder for Redevelopment of Thiruvananthapuram Central Railway Station