ACME Solar Commissions More BESS Capacity at Rajasthan FDRE Project

ACME Solar commissioned 16.06 MW and 35.81 MW of BESS discharge capacity at its Chittorgarh, Rajasthan FDRE projects on Nov 20, 2026. COD is Nov 22.
ACME Solar Commissions More BESS Capacity at Rajasthan FDRE Project

Gurugram: ACME Solar Holdings Limited has told BSE and NSE that its wholly owned subsidiary, ACME Sigma Urja Private Limited, commissioned more battery energy storage system (BESS) capacity on November 20, 2026. The capacity is at two FDRE (firm and dispatchable renewable energy) projects at Neemri village, Rawatbhata tehsil, Chittorgarh district, Rajasthan. The commercial operation date (COD) for both is November 22, 2026.

What Was Commissioned?

Detail

Filing 1: 250 MW FDRE Project

Filing 2: Tata FDRE Power Project (BESS part)

Capacity commissioned today (discharge)

16.06 MW / 69.678 MWh

35.81 MW / 148.645 MWh

Installed capacity of this tranche

16.06 MW / 75.225 MWh

35.81 MW / 160.48 MWh

Total project BESS discharge capacity

250 MW / 1,069 MWh

50 MW / 209 MWh

Total project BESS installed capacity

250 MW / 1,150 MWh

50 MW / 220 MWh

Commissioned on

November 20, 2026

November 20, 2026

COD

November 22, 2026

November 22, 2026

Follow PSU Connect:WhatsApp

Cumulative Progress

ACME says ACME Sigma Urja has now reached a cumulative commissioned BESS discharge capacity of 175.72 MW / 733.939 MWh, with installed capacity of 175.72 MW / 792.418 MWh. This update continues an earlier intimation dated October 31, 2026.

Tata Power PPA

For the Tata FDRE Power Project, the company says only the BESS component has been commissioned so far. The power purchase agreement (PPA) for this project is signed with The Tata Power Company Limited.

What the Filings Do Not Say

The filings do not say whether the 35.81 MW tranche is included in the 175.72 MW cumulative figure, or how the 250 MW and 50 MW projects relate to each other. They also do not give tariffs, project costs or the date the remaining capacity will be commissioned. We have not added the two tranches together or estimated any of these.

Follow PSU Connect:LinkedIn

Note*: This article is for informational purposes only. PSU Connect is not responsible for any actions taken based on this content.Terms & Conditions