ACME Solar Commissions More BESS Capacity at Rajasthan FDRE Project
Gurugram: ACME Solar Holdings Limited has told BSE and NSE that its wholly owned subsidiary, ACME Sigma Urja Private Limited, commissioned more battery energy storage system (BESS) capacity on November 20, 2026. The capacity is at two FDRE (firm and dispatchable renewable energy) projects at Neemri village, Rawatbhata tehsil, Chittorgarh district, Rajasthan. The commercial operation date (COD) for both is November 22, 2026.
What Was Commissioned?
|
Detail |
Filing 1: 250 MW FDRE Project |
Filing 2: Tata FDRE Power Project (BESS part) |
|---|---|---|
|
Capacity commissioned today (discharge) |
16.06 MW / 69.678 MWh |
35.81 MW / 148.645 MWh |
|
Installed capacity of this tranche |
16.06 MW / 75.225 MWh |
35.81 MW / 160.48 MWh |
|
Total project BESS discharge capacity |
250 MW / 1,069 MWh |
50 MW / 209 MWh |
|
Total project BESS installed capacity |
250 MW / 1,150 MWh |
50 MW / 220 MWh |
|
Commissioned on |
November 20, 2026 |
November 20, 2026 |
|
COD |
November 22, 2026 |
November 22, 2026 |
Cumulative Progress
ACME says ACME Sigma Urja has now reached a cumulative commissioned BESS discharge capacity of 175.72 MW / 733.939 MWh, with installed capacity of 175.72 MW / 792.418 MWh. This update continues an earlier intimation dated October 31, 2026.
Tata Power PPA
For the Tata FDRE Power Project, the company says only the BESS component has been commissioned so far. The power purchase agreement (PPA) for this project is signed with The Tata Power Company Limited.
What the Filings Do Not Say
The filings do not say whether the 35.81 MW tranche is included in the 175.72 MW cumulative figure, or how the 250 MW and 50 MW projects relate to each other. They also do not give tariffs, project costs or the date the remaining capacity will be commissioned. We have not added the two tranches together or estimated any of these.