NHPC Settles Parbati-III Dispute With Patel-L&T Consortium for ₹42.62 Crore

NHPC settled a Parbati-III HE Project dispute with the Patel-L&T Consortium for ₹42.62 crore via CCIE-III against an earlier claim of ₹256.10 crore, releasing payment on November 17, 2026.
NHPC Settles Parbati-III Dispute With Patel-L&T Consortium for ₹42.62 Crore

New Delhi: NHPC Limited has entered into a settlement agreement with the Patel-L&T Consortium (PLNT) to resolve a dispute under the Parbati-III Hydroelectric (HE) Project (Ref. II) through the Conciliation Committee of Independent Experts (CCIE-III).

In a regulatory filing submitted to the stock exchanges under Regulation 30 of the SEBI (Listing Obligations and Disclosure Requirements) Regulations, 2015, NHPC disclosed that the matter was settled for ₹42.62 crore, compared to the ₹256.10 crore originally claimed by PLNT.

Follow PSU Connect:WhatsApp

Key Details of the Settlement

  • Project & Counterparty: The dispute pertained to claims arising from site handover delays, adverse geological conditions, and related factors under the Parbati-III HE Project (Ref. II) involving the Patel-L&T Consortium (PLNT), continuing from NHPC's earlier disclosure dated August 14, 2023.

  • Settlement Amount vs. Claim: The final agreed settlement stands at ₹42.62 crore, down from PLNT's earlier claim of ₹256.10 crore.

  • Payment & Withdrawal of Claims: NHPC released the ₹42.62 crore settlement amount to PLNT on November 17, 2026, and both PLNT and NHPC have withdrawn their respective claims.