Rourkela Steel Plant Revives CNC Machine Idle Since 2022

SAIL’s Rourkela Steel Plant revived the CR3000 CNC machine at its Raw Material Handling Plant on Nov 10, 2026, using in-house teams after four years idle.
Rourkela Steel Plant Revives CNC Machine Idle Since 2022

SAIL’s Rourkela Steel Plant (RSP) has brought back into service a CR3000 CNC machine that had not worked since 2022. The machine is at the Phase-III Workshop of the Raw Material Handling Plant (RMHP) and became operational on November 10, 2026, according to the plant’s official social media post. The plant says in-house teams carried out the revival.

What Happened

The CR3000 CNC machine had been non-operational since 2022. The Mechanical and Electrical teams of RMHP restored it by working together. Two other units supported them:

  • Mechanical Shop: technical support

  • Roll Shop: consumables support during the revival

Follow PSU Connect:WhatsApp

Who Worked on It

Team

Members named by RSP

Mechanical

S. Bhanjdeo and S. Mallick (AGMs); D.K. Patel and B.B. Nayak (Junior Engineers); H.K. Dhal (Junior Engineering Associate)

Electrical

C. Magar and B.K. Behera (AGMs); S.K. Gouda and K. Nayak (Junior Engineers); P.K. Rout (Assistant Manager)

Why It Matters

According to RSP, the revival should:

  • Reduce dependence on external agencies for machining work

  • Improve workshop productivity

  • Strengthen maintenance readiness at RMHP

Follow PSU Connect:LinkedIn

The Raw Material Handling Plant handles the raw materials used in steelmaking at the plant. The post describes the revival as a boost to RMHP’s in-house machining and maintenance capability.

Note*: This article is for informational purposes only. PSU Connect is not responsible for any actions taken based on this content.Terms & Conditions