THDC India Completes Hydrostatic Testing of Unit 3 Spiral Casing at 444 MW Vishnugad-Pipalkoti Project

THDC India completes hydrostatic testing of Unit 3 spiral casing at the 444 MW Vishnugad-Pipalkoti hydro project, pressurised to 48 kg/cm² in six hours.
THDC India Completes Hydrostatic Testing of Unit 3 Spiral Casing at 444 MW Vishnugad-Pipalkoti Project

New Delhi: THDC India Limited has successfully completed hydrostatic testing of the spiral casing of Unit 3 at its 444 MW Vishnugad-Pipalkoti Hydro Electric Project (VPHEP) in Uttarakhand. The casing was filled with clear water and pressurised up to 48 kg/cm², and the full test was finished within six hours, the company said.

The test is a key step in the erection and commissioning work of the third generating unit at the project.

What Was Tested and How

During the test, the spiral casing was filled with clear water and the internal pressure was raised gradually. THDC says the pressure build-up followed the pressure-time schedule laid down in the approved drawings, reaching 48 kg/cm². According to the company, the procedure met the required technical, quality and safety standards.

Follow PSU Connect:WhatsApp

What Is a Spiral Casing, and Why Is This Test Important?

The spiral casing is a snail-shaped steel structure in a hydropower unit. It guides water evenly towards the turbine. A hydrostatic test checks that the casing can hold high water pressure without leaks or structural problems before it is embedded in concrete and the unit moves ahead. Passing it means the unit can proceed to later stages of installation.

What THDC Officials Said

THDC India's Managing Director, Sipan Kumar Garg, congratulated the VPHEP team and called it an important milestone. He praised the team's technical expertise and the effort of the agencies involved, and stressed the need for continued coordination.

Ajay Verma, Executive Director (Projects), also congratulated the team and highlighted close monitoring and coordination of project activities.

Dr. Niraj Kumar Agrawal, Head of Project (VPHEP), explained the technical significance of the test and briefed those present on the procedure and the key parameters achieved.

Senior officers present included General Manager (EM) Ravindra Singh Rana, Additional General Manager (HM) Sanjay Mamgain and Additional General Manager (G&G) Ajay Kumar.

 

Follow PSU Connect:LinkedIn

About the Vishnugad-Pipalkoti Hydro Electric Project

VPHEP is a run-of-the-river project on the Alaknanda river in Chamoli district, Uttarakhand. It has four units of 111 MW each, adding up to 444 MW. A similar test on Unit 2's spiral casing was completed in December 2025.

An earlier THDC progress update had set targets of commissioning the first unit by March 2027 and the last unit by September 2027. Those timelines may have changed, so check THDC's latest updates.

The project was also in the news in August 2026, when a landslide and debris inflow in an under-construction tunnel led to a rescue operation and, according to media reports, deaths among workers.