NHPC completes Renovation and Modernization its 180 MW Baira Siul Power Station and commenced commercial operation
After R&M works, the life of Baira Siul Power Station has now been extended by another 25 years.
New Delhi: NHPC Ltd, India’s premier hydropower company with its competent manpower has indigenously and successfully renovated & modernized its 180 MW Baira Siul Power Station and commenced commercial operation.
The Baira Siul Power Station is NHPC’s first power station which was under commercial operation since 1st April 1982 and had completed its useful life of 35 years.
The renovation and modernization of all three units has been successfully completed. NHPC has commenced commercial operation of Unit #2 & Unit #1 on 00:00 Hrs. of 29.12.2019 and 00:00 Hrs. of 07.11.2020 respectively. The third Unit (Unit #3) has been declared under commercial operation on 00:00 Hrs. of 31.08.2021. As such after R&M works, NHPC has commenced commercial operation of all the three Units (3 x 60 MW) of Baira Siul Power Station.
After R&M works, the life of Baira Siul Power Station has now been extended by another 25 years. NHPC’s technical expertise with its persistent efforts along with high level of professionalism has been instrumental in achieving this milestone.
Read Also : CDSL Q4 result, Net profit doubles to Rs 129 cr in Q4News Must Read
- BPCL signs agreement with Noida International Airport
- Indian Bank Q4 results, net profit up by 6 percent on Quarter basis
- PSU Stocks tumbled amid RBI draft circular on lenders
- Paytm share price plunges 4% as president and COO Bhavesh Gupta resigns
- GAIL Global USA and Kinder Morgan Operating LLC signed MOU
- SJVN signs agreement with Tata Power RE for 460 MW Renewable Energy Project
- Keel Laying of the First Next Generation Offshore Patrol Vessel At Goa Shipyard Ltd
- REC Ltd received NOC to set up wholly owned subsidiary in Gift City, Gujarat
- Atanu Chakraborty Reappointed as part-time Chairman of HDFC Bank
- MRPL Q4 Results: Net profit slips 40%, Annual Gains Strong