NTPC in Andhra Pradesh lags behind in power generation

KARIMNAGAR .The shortage of coal supply from the Singareni Collieries Company Limited (SCCL) following the incessant rains during the monsoon season and the frequent tripping of power stations had forced the National Thermal Power Corporation (NTPC), Ramagundam, lag behind in power generation during this financial year of 2013-14.
Against the target of generating 15,286 million units of power till January 1, 2014 (during the nine months period of the financial year), the NTPC could generate only 14,410 million units.
During the year 2012-13, the NTPC generated 20,785 million units of power against the target of generating 20,448 MU. Following its performance, the NTPC was fixed a target of generating 20,708 million units during the year 2013-14. However, it was short of 876 MU during the nine month period.