GAIL revises completion schedule for 1702 Km long MNPL Pipeline project

The revision date has been shifted from 30th September 2025 to 31st December 2025 progressively.

GAIL revises completion schedule for 1702 Km long MNPL Pipeline project

New Delhi, September 24, 2025: State-owned GAIL (India) Ltd. has revised the completion schedule for the MUMBAI-NAGPUR-JHARSUGUDA PIPELINE PROJECT (MNPL), which is 1702 km long. It was approved by the Board of Directors of the Company in its meeting held on 24.09.2025.

• Mumbai–Nagpur Pipeline (Part-A): 693 Km

• Nagpur-Jharsuguda Pipeline (Part-B): 692 Km

• Nagpur-Jabalpur Pipeline (Part-C): 317 Km

The revision date has been shifted from 30th September 2025 to 31st December 2025 progressively.

Join PSU Connect on WhatsApp now for quick updates! Whatsapp Channel

Read Also : RECPDCL Handsover Davanagere Power Transmission SPV to PowerGrid

Mumbai-Nagpur Pipeline (Part-A): The pipeline is mechanically completed. PESO site inspection completed, permission awaited.

Nagpur-Jharsuguda Pipeline (Part-B): Odisha and Chhattisgarh (489 Km)—Thepipeline is mechanically completed and ready for gas-in. PESO site inspection completed, permission awaited.

Maharashtra (203 km): Pipeline work of around 9 km is balanced. The work is in progress and expected to be ready for gas-in by December 2025.

Nagpur-Jabalpur Pipeline (Part C): Madhya Pradesh (255 Km): The pipeline is mechanically completed.

Maharashtra (62 Km): Pipeline work of around 1.8 Km is balanced and is expected to be completed by October, 2025.

Therefore, the entire Mumbai-Nagpur-Jharsuguda pipeline is expected to be completed progressively by 31st December 2025.