NTPC Renewable Energy Announces O&M Tender for Khavda Renewable Energy Park

NTPC Renewable Energy has invited bids for a 3-year operation and maintenance contract for four pooling substations at its 4.75 GW Khavda Renewable Energy Park in Gujarat.
NTPC Renewable Energy Announces O&M Tender for Khavda Renewable Energy Park

NTPC Renewable Energy Limited (NREL) has issued a tender for the operation and maintenance of four pooling substations at its 4.75 GW Khavda Renewable Energy Park in Gujarat. The contract duration will be three years.

The tender has been published on the GeM portal under Bid Number GEM/2026/B/7706808. Interested bidders can submit their offers until 21 July 2026 at 3:00 PM, while technical bids will be opened on the same day at 3:30 PM.

 

Key Tender Details

  • Project: Operation and Maintenance of 4 Pooling Substations

  • Location: Khavda RE Park, Bhuj, Gujarat

  • Contract Period: 3 Years

  • Bid Submission Deadline: 21 July 2026

  • Bid Opening: 21 July 2026

  • EMD: ₹20 lakh

  • Tender Type: Single Stage, Two-Envelope Bid

  • Reverse Auction: Not Applicable

 

Follow PSU Connect:WhatsApp

Eligibility Criteria

The tender is open only to Class-I Local Suppliers under the Government's Make in India policy.

To qualify, bidders must have previous experience in either:

  • Installation and commissioning of 220 kV or higher voltage substations, or

  • Operation and maintenance of 220 kV or higher voltage substations for at least one year during the last seven years.

The bidder should also have an average annual turnover of at least ₹3.56 crore during the previous three financial years and meet the prescribed net worth requirements.

 

Project Significance

The Khavda Renewable Energy Park is among India's largest renewable energy developments. Reliable operation of its pooling substations is essential for transmitting electricity generated from large-scale solar and wind projects.

The selected contractor will be responsible for maintaining these substations, ensuring uninterrupted operations, equipment reliability, safety compliance, and quick response to any technical issues throughout the three-year contract period.

The tender reflects NTPC Renewable Energy's continued focus on maintaining high operational standards while supporting India's clean energy expansion and power infrastructure development.

The successful bidder will be expected to mobilize within seven days of the Letter of Award and comply with all safety, quality, and statutory requirements specified in the tender documents.