EIL with GAIL achieved a major milestone

EIL with GAIL achieved a major milestone

New Delhi: Team EIL along with Team GAIL-Usar achieved a major milestone with the completion of the second part of the RCC pour for the CATOFIN Reactor Structure for the 500 KTA PDH-PP Petrochemical Plant being set up by GAIL (India) Limited at Usar, Maharashtra.

Join PSU Connect on WhatsApp now for quick updates! Whatsapp Channel CE-MAT 2025

Read Also : Varun Kumar Shukla to be next CMD of Hindustan Salts Ltd

The second part, 2845 Cum, of the total RCC quantity, 6154 Cum, for the reactor structure is one of the highest single-pour RCCs for the PDH-PP project.