ISRO carried first integrated test on Semicryogenic engine at IPRC, Mahendragiri

The test on May 10, 2023, is a major milestone before integrating the complete engine and its qualification.

ISRO carried first integrated test on Semicryogenic engine at IPRC, Mahendragiri
Semicryo Test Stand

New Delhi: ISRO on May 10 carried out the first integrated test on an intermediate configuration of the 2000kN Semicryogenic Engine at the newly commissioned Semicryogenic Integrated Engine & Stage Test facility at the ISRO Propulsion Complex (IPRC), Mahendragiri.

The intermediate configuration, designated as Power Head Test Article (PHTA), comprises all the engine systems except the thrust chamber. The test is the first of a series of tests planned to validate the design of the propellant feed system, including the low-pressure and high-pressure turbo-pumps, the gas generator, and control components.

Read Also : Indian Air Force ushers in Digital Transformation with DigiLocker Integration

ISRO's Liquid Propulsion Systems Centre 

The Liquid Propulsion Systems Centre (LPSC) of ISRO has undertaken the design &development of a Semicryogenic engine with 2000 kN thrust with Indian industry participation, and will power the booster stages of future launch vehicles and works on Liquid Oxygen (LOX)-Kerosene propellant combination.

The test on May 10, 2023, is a major milestone before integrating the complete engine and its qualification. This test demonstrated the complex chill-down operations spanning about 15 hours duration that was conducted successfully, meeting all the required conditions for engine start.

After the chill down of the LOX circuit, the feed circuit of kerosene was filled, and LOX was admitted into the gas generator by opening the injection valve. Successful performance of the test article helps derive the sequence of operations for further tests.

 

Read Also : 19th Meeting of TOLIC (U) of Bhubaneswar organized at NALCO

The newly established test facility at IPRC, Mahendragiri, with a state-of-art PLC-based control system and data acquisition system, is capable of testing semi-cryogenic engines up to 2600 kN thrust and will support the subsequent testing and qualification of the fully integrated Semicryogenic engine and stage.

This test has demonstrated the successful performance of the test facility and power head test article in the first attempt itself.