NHPC’s Kiru HEP Achieves Major Milestone with 12 Lakh Cum Dam Concreting

NHPC’s 624 MW Kiru Hydroelectric Project under CVPPL has completed 12.00 lakh cubic metres of dam concreting out of 12.20 lakh cum. Dam construction targeted for completion by August 2026.
NHPC’s Kiru HEP Achieves Major Milestone with 12 Lakh Cum Dam Concreting

New Delhi, August 1, 2026: The 624 MW Kiru Hydroelectric Project has achieved a significant construction milestone.

Chinab Valley Power Projects Limited (CVPPL) has successfully completed 12.00 lakh cubic metres of dam concreting out of the total 12.20 lakh cubic metres.

With this progress, the project is moving rapidly towards completion of the dam by August 2026. This will pave the way for commissioning of the project by March 2027.

 

Advertisement
Follow PSU Connect:WhatsApp

 

Shri Bhupender Gupta, Chairman & Managing Director, NHPC; Shri Sanjay Kumar Singh, Director (Projects), NHPC; Shri Suprakash Adhikari, Director (Technical), NHPC; and Shri Ramesh Mukhiya, Managing Director, CVPPL, have congratulated the entire Kiru HEP team and the executing agency, M/s Patel Engineering Limited, on this achievement.

 

Advertisement
Follow PSU Connect:LinkedIn

 

On the occasion, Shri Ramesh Mukhiya, MD, CVPPL, emphasised the need to complete the remaining milestones within the stipulated timelines. This will ensure successful commissioning of the project during the financial year 2026–27.

The Kiru HEP is a key project in the Chenab basin and forms an important part of NHPC’s hydropower expansion plans.

Source: Official update from NHPC Limited / Chinab Valley Power Projects Limited.