Rishikesh-Karnaprayag Rail: 6.59 km Tunnel-14 Breakthrough Achieved in Rudraprayag

Indian Railways has completed the main breakthrough of the 6.59 km Tunnel-14 on the Rishikesh-Karnaprayag rail project in Rudraprayag. See how it was dug.
Rishikesh-Karnaprayag Rail: 6.59 km Tunnel-14 Breakthrough Achieved in Rudraprayag

New Delhi: Indian Railways has completed the main breakthrough of Tunnel-14 on the Rishikesh-Karnaprayag rail project in Uttarakhand's Rudraprayag district, the Press Information Bureau announced on 27 November 2026. The 6.59 km tunnel is now connected end to end.

How the Tunnel Was Dug

The breakthrough joins two excavated sections:

  • 4.7 km driven from Portal-1 (Sumerpur)

  • 1.79 km driven from Portal-2 (Marora)

Advertisement
Follow PSU Connect:WhatsApp

Tough Ground at Both Ends

  • Portal-1: A 110-metre stretch of the triple-track tunnel ran through loose soil under inhabited areas, with 20-30 metres of soil and rock above. Engineers used pre-excavation and multi-drifting to dig safely. The 4.7 km drive also had specialised ventilation to supply fresh air and control temperature.

  • Portal-2: The slope was secured with 30-35 metre deep micropiles, 15-20 metre long rock bolts and consolidation grouting. This allowed the main tunnel drive to start in March 2024, after ground settlement issues at Marora and land and house acquisition matters were resolved. About 100 metres was dug mechanically.

  • Blasting: Controlled blasting was done only in daytime near both portals to protect nearby settlements.

About the Rishikesh-Karnaprayag Project

The 125 km broad-gauge line is being built by Rail Vikas Nigam Limited (RVNL) and will connect Rishikesh, Devprayag, Srinagar, Rudraprayag, Gauchar and Karnaprayag. About 105 km of the route is in tunnels. When it opens, travel between Rishikesh and Karnaprayag is expected to fall from about seven hours to about two.

Earlier milestones include the 14.57 km Tunnel-8 breakthrough in April 2025, using the tunnel boring machine "Shakti". It is India's longest transport tunnel.

Railways says the line will improve access to the hill regions, help pilgrims and tourists, and support regional development.

Official source: Press Information Bureau (PIB) release, 27 November 2026: https://pib.gov.in