GAIL completes Longest HDD in Odisha

An innovative technique of electromagnetic steering was used to enable the Single Shot Pipe Pulling, beneath the river.
GAIL completes Longest HDD in Odisha

New Delhi: GAIL (India) Limited completes the Longest HDD (Horizontal Directional Drilling) of 3.821 km, across the Mahanadi River in Odisha on 6th July 2023 in the SAPL (Srikakulam-Angul Pipeline) Project. 

Advertisement

An innovative technique of electromagnetic steering was used to enable the Single Shot Pipe Pulling, beneath the river. 

Advertisement

The milestone was achieved by meticulous planning and execution by our team of experts and our partners, M/s MECON and M/s Trenchless Engg. Services Pvt Ltd.