NHPC updates on unit-3 of Baira Siul Power Station in Himachal Pradesh
The company Unit-3 of Baira Siul Power Station in Himachal Pradesh has been synchronized with the grid on August 22, 2021, after completion of its R&M

National Hydroelectric Power Corporation unit-3 of Baira Siul Power Station in Himachal Pradesh
New Delhi: National Hydroelectric Power Corporation updates unit-3 of Baira Siul Power Station in Himachal Pradesh. The company Unit-3 of Baira Siul Power Station in Himachal Pradesh has been synchronized with the grid on August 22, 2021, after completion of its R&M
NHPC said in the regulatory filing that the company Unit-3 of Baira Siul Power Station in Himachal Pradesh has been synchronized with the grid on August 22, 2021, after completion of its R&M.
"In continuation to our earlier letters of even number dated 16.10.2018, 28.12.2019 and 08.11 .2020, it is to inform that Unit #3 of Baira Siul Power Station (3 X 60 MW) in Himachal Pradesh has been synchronized with grid on 22.08.2021 (12:10 Hrs) after completion of its Renovation and Modernization work,” the company said in the filing.